Following completion of the strong floor and reaction mass (in excess of 2000tonnes of steel and concrete), the main contractors have commenced the erection of the steel frame for the building. This phase is expected to take approximately 3 weeks and following this construction of the building envelope will commence. The scale of the building is now apparent, with the ridgeline being approximately 13m above the finish floor level giving an 8m clearance for the gantry crane inside the building.