Site progress update

Much progress on the construction of SoFSI has been made in the last month following a sustained period of good weather. The steel frame for both the test hall and the accommodation block are now complete and the main contractor, Andrew Scott Ltd, are now preparing for the final interior concrete pours to form the remaining floor slab in both parts of the building.

With the roof near completion on the accommodation block it provided a great viewpoint to see the scale of both the soil pit and the pit for the large shaking table.

Following completion of the floor slabs the next steps are to install the gantry crane, complete the roof of the test hall and start the blockwork walls to the test hall. If all goes to programme the building should be water tight before the end of the year.