SoFSI Blog

Hexapod moves to SoFSI

The final major piece of equipment has now arrived at SoFSI, with our six degree of freedom shaking table making the move from Queen’s Building to its permanent home in Langford. With decommissioning in Queen’s Building starting in mid-August, the Hexapod was moved and recommissioned at SoFSI by mid-September. The higher pressure and flow rate of the hydraulic system here allows the Hexapod to reach its full triaxial performance of 8g with a 500kg payload. Since moving, it has already successfully been put to use for seismic qualification work.

Small yellow shaking table with blue hydraulic actuators and base plate in position.

First research project underway

Construction is complete on our first research project at the Soil-Foundation-Structure Interaction Laboratory. This project, which makes use of our 4m deep soil pit, has been under construction since late May. Researchers aim to better understand the interaction between the abutment and backfill of integral bridge abutments.

We are now at an exciting stage in the project, having completed the physical construction, and are now preparing instrumentation ready for testing in August. In total, over 100 tonnes of concrete and sand form the experimental set-up, and this has been a great opportunity to pilot the use of the pit, and hydraulic actuator for the first time.

  • A 4m deep pit, with precast concrete blocks being positioned to form a retaining wall

Shaking table commissioned

In December the large biaxial shaking table underwent commissioning testing. This involved operating the table for the first time and checking all safety and performance functions, followed by validating its performance against the original specification. It was great to see it in motion and we’re looking forward to the training and using it in anger later this year.

Shaking table installed

Another major milestone was passed at the end of September as the 30 tonne surface of our biaxial shaking table was lifted into its final position. The four actuators have since been installed around the table, and once the final hydraulic hoses have been connected, physical installation within the facility will be complete. The next significant event will be acceptance testing of the table which is expected towards the end of November, and will mark the final activity before the faculty is handed to the University.

Wide angle view of the yellow painted shaking table with machined surface in position within its pit.
The 6x4m shaking table in position.

Crane installed


Today the 30t gantry crane was commissioned. This will enable both the filling and emptying of the test pit, and the lifting of test items off the two shaking tables within SoFSI. In addition to this further milestones were achieved this week with the switching on of the high-voltage electricity supply to the laboratory, the laying of the resin floor finish within the test hall and the commencement of the slab within the service yard.

Site progress update – building shell watertight

Prior to the Christmas break the SoFSI building envelope was completed and the building was watertight. With scaffolding both inside and outside the building it was a great chance to appreciate the full scale of the facility by being able to climb above the height of the 30t gantry crane – a view which will not be available once the facility is open. Now the building shell is complete we are looking forward to the final fit out followed by the installation of the hydaulic equipment – the pit in the centre of the above photograph is to receive our 50t capacity, 6m x 4m biaxial shaking table.

 

Site progress update

Much progress on the construction of SoFSI has been made in the last month following a sustained period of good weather. The steel frame for both the test hall and the accommodation block are now complete and the main contractor, Andrew Scott Ltd, are now preparing for the final interior concrete pours to form the remaining floor slab in both parts of the building.

With the roof near completion on the accommodation block it provided a great viewpoint to see the scale of both the soil pit and the pit for the large shaking table.

Following completion of the floor slabs the next steps are to install the gantry crane, complete the roof of the test hall and start the blockwork walls to the test hall. If all goes to programme the building should be water tight before the end of the year.

Steel erection commences

Following completion of the strong floor and reaction mass (in excess of 2000tonnes of steel and concrete), the main contractors have commenced the erection of the steel frame for the building. This phase is expected to take approximately 3 weeks and following this construction of the building envelope will commence. The scale of the building is now apparent, with the ridgeline being approximately 13m above the finish floor level giving an 8m clearance for the gantry crane inside the building.